Skip to Content

Related News

  • Related News

  • EWEB opens application for 2024 Electric Mobility Community Grants

    Grant awards of up to $30,000 to cover costs associated with electric mobility projects.

    Find Out More
  • Upgrades to Eugene's downtown electric network continue

    You may have noticed construction this week on the corner of 7th and Pearl Street. That’s because crews replaced a corroded, aging vault with an innovative, new Voltek vault. The Voltek design allows for the new infrastructure to be built inside of the existing aging vault. We’re able to install the new vault while the cables are still energized, minimizing disruption to customers and traffic while cutting construction time in half.

    Find Out More
  • The Big Freeze 2024: After Action Report

    Winter 2024 was one for the records books, and we'll look back on it for years to come and say, "That was a doozy!"  The back-to-back January Ice Storms caused widespread damage to EWEB’s service territory, affecting approximately 38,000 customers. Preliminary repair costs were over $8 million, and additional repairs to transmission lines are still required. 

    Find Out More
  • Celebrate Earth Month by taking charge of your home's energy use

    This Earth Month, learn how you can reduce your energy usage to help protect our planet and reduce carbon emissions.

    Find Out More
  • Spring Cleaning? How about Spring Emergency Preparedness!

    Spring is officially here and that means the plants are blooming, the sun is (sometimes) shining, and the grass is green! We've had our fair share of severe weather already, but spring weather is notoriously unpredictable. While you're in the midst of spring cleaning and garden care, consider completing these emergency preparedness tasks.

    Find Out More
  • Show More
EWEB Project Underway Reduces Maintenance Costs and Improves Wildfire Mitigation along McKenzie Highway

August 01, 2022

EWEB’s removal of 31 miles of electric conductor and 159 poles spanning five miles along the McKenzie Highway is now underway. This removal project will improve the community's aesthetic, reduce maintenance costs, and decrease environmental impact. 

“The decision to get rid of the lines, instead of rebuilding them, will increase customer reliability and allow us to connect to the broader system more efficiently while reducing wildfire risk,” said Tyler Nice, EWEB Electric Division Manager.  

This unique opportunity to reduce the infrastructure footprint and maintenance costs will also improve wildfire mitigation because less infrastructure means less chance of ignition or damage from a fire. 

“Removing these transmission lines is just the right thing to do,” said Jebediah Wolfe, EWEB Project Manager, “having the poles up and wires attached is unnecessary at this point.” 

The poles, supporting two, 3-phase circuits, once transmitted power from the Walterville substation to the Leaburg substation. The lines were de-energized in 2019 as part of the Holden Creek substation project. The Holden Creek substation improved the resiliency of our McKenzie River transmission system by replacing the Leaburg substation, originally built in the early 1930s. Replacing the lines was one of several options, but ultimately, EWEB opted to pay a small interconnection fee to use the existing, adjacent power lines owned by the Bonneville Power Administration. This decision was cost-effective because the estimate for repairing and replacing the current lines was $10.6 million.  

The decision to use Bonneville’s existing lines saved EWEB millions of dollars and provided the opportunity to lessen the community impact. Many of the poles scheduled for removal are on private property – in fields, over houses and driveways. Private property owners will appreciate the removal and restoration on their land. 

While this project is exciting for the local community, it’s important to note that this was a unique opportunity to plan new projects and use existing infrastructure strategically to avoid costs while reducing footprint and impact. 

“I’m so proud of our team for thinking outside the box and coming up with an alternative to the standard ‘replace-in-kind’ approach,” said Nice.

EWEB crews will be hard at work removing the transmission lines and poles throughout the summer, and we anticipate project completion in September of 2022.