Skip to Content

Related News

  • Related News

  • Watch the Recording: Financial Preparedness for Disasters

    How will you financially recover after a disaster? This seminar gives key insights into preparing your finances ahead of time.

    Find Out More
  • Greenpower subscribers vote to award Greenpower Grant to SquareOne Villages

    The Greenpower Grant, funded solely by voluntary customer subscriptions, supports local sustainability projects.

    Find Out More
  • EWEB reaffirms commitment to resilience with Wildfire Mitigation Plan approval

    The utility is testing new equipment, leveraging technology, and incorporating third-party expertise to bolster electric system resiliency to a range of threats, including wildfire.

    Find Out More
  • Energy conservation could offset large portion of growth in power demand

    Preliminary results of an EWEB study indicate that cutting back demand can contribute to maintaining a reliable, affordable energy supply.

    Find Out More
  • Groups suing EWEB will burden customers with litigation-driven costs

    EWEB expresses disappointment that groups choose court over collaboration and firmly disputes the claims made in the lawsuit relating to operation of the utility’s Carmen-Smith Hydroelectric Project nearly 70 miles east of Eugene. EWEB takes its environmental and public safety responsibilities seriously. Contrary to the assertions in the lawsuit, construction of fish passage was postponed because EWEB’s regulator, the Federal Energy Regulatory Commission (FERC), required the utility to study and resolve urgent dam safety issues first.

    Find Out More
  • Show More
EWEB Project Underway Reduces Maintenance Costs and Improves Wildfire Mitigation along McKenzie Highway

August 01, 2022

EWEB’s removal of 31 miles of electric conductor and 159 poles spanning five miles along the McKenzie Highway is now underway. This removal project will improve the community's aesthetic, reduce maintenance costs, and decrease environmental impact. 

“The decision to get rid of the lines, instead of rebuilding them, will increase customer reliability and allow us to connect to the broader system more efficiently while reducing wildfire risk,” said Tyler Nice, EWEB Electric Division Manager.  

This unique opportunity to reduce the infrastructure footprint and maintenance costs will also improve wildfire mitigation because less infrastructure means less chance of ignition or damage from a fire. 

“Removing these transmission lines is just the right thing to do,” said Jebediah Wolfe, EWEB Project Manager, “having the poles up and wires attached is unnecessary at this point.” 

The poles, supporting two, 3-phase circuits, once transmitted power from the Walterville substation to the Leaburg substation. The lines were de-energized in 2019 as part of the Holden Creek substation project. The Holden Creek substation improved the resiliency of our McKenzie River transmission system by replacing the Leaburg substation, originally built in the early 1930s. Replacing the lines was one of several options, but ultimately, EWEB opted to pay a small interconnection fee to use the existing, adjacent power lines owned by the Bonneville Power Administration. This decision was cost-effective because the estimate for repairing and replacing the current lines was $10.6 million.  

The decision to use Bonneville’s existing lines saved EWEB millions of dollars and provided the opportunity to lessen the community impact. Many of the poles scheduled for removal are on private property – in fields, over houses and driveways. Private property owners will appreciate the removal and restoration on their land. 

While this project is exciting for the local community, it’s important to note that this was a unique opportunity to plan new projects and use existing infrastructure strategically to avoid costs while reducing footprint and impact. 

“I’m so proud of our team for thinking outside the box and coming up with an alternative to the standard ‘replace-in-kind’ approach,” said Nice.

EWEB crews will be hard at work removing the transmission lines and poles throughout the summer, and we anticipate project completion in September of 2022.