Skip to Content

Related News

  • Related News

  • Upgrades to Eugene's downtown electric network continue

    You may have noticed construction this week on the corner of 7th and Pearl Street. That’s because crews replaced a corroded, aging vault with an innovative, new Voltek vault. The Voltek design allows for the new infrastructure to be built inside of the existing aging vault. We’re able to install the new vault while the cables are still energized, minimizing disruption to customers and traffic while cutting construction time in half.

    Find Out More
  • The Big Freeze 2024: After Action Report

    Winter 2024 was one for the records books, and we'll look back on it for years to come and say, "That was a doozy!"  The back-to-back January Ice Storms caused widespread damage to EWEB’s service territory, affecting approximately 38,000 customers. Preliminary repair costs were over $8 million, and additional repairs to transmission lines are still required. 

    Find Out More
  • Spring Cleaning? How about Spring Emergency Preparedness!

    Spring is officially here and that means the plants are blooming, the sun is (sometimes) shining, and the grass is green! We've had our fair share of severe weather already, but spring weather is notoriously unpredictable. While you're in the midst of spring cleaning and garden care, consider completing these emergency preparedness tasks.

    Find Out More
  • Nine days without power: My ice storm story as an EWEB customer and employee

    While beautiful and peaceful, buying a home on the edge of the forest and surrounded by trees has its tradeoffs. Moving “upriver,” I knew there would be more threats to prepare for, including Mother Nature’s seasonal surprises.

    Find Out More
  • Leaburg Decommissioning Action Plan

    Plan details next steps through regulatory processes to begin dismantling Leaburg Dam by 2032.

    Find Out More
  • Show More
EWEB explores options for remediating Leaburg Canal

April 11, 2022

Leaburg Canal

EWEB is moving forward with analyzing four options to remediate the Leaburg Canal, ranging from full decommissioning to complete restoration, with two options in between. 

Changes are needed on the Leaburg Canal, which was built in the 1920s, because of increased seepage and internal erosion of the canal embankments that was discovered in 2018. Since then, EWEB has operated the canal as a stormwater conveyance facility, and it has not generated electricity.

During the entire process, safety has been EWEB’s top priority, for both the community and local residents near the canal.

In late 2019, EWEB started a comprehensive assessment of the canal to better understand the level of investment that would be required to ensure long-term safe and reliable operation. EWEB is currently working with consultants to conduct a Triple Bottom Line (TBL) assessment to analyze the financial, environmental and social impacts of multiple repair alternatives for the canal – a process that will be ongoing throughout 2022.

Four alternatives have emerged that EWEB will study in further detail. The alternatives range from full decommissioning to a complete return to service, and each prioritizes the safety of EWEB employees and the community. 

  • Alternative 1: The full removal of all facilities to pre-project conditions – as if the Leaburg Project were never built. 
  • Alternative 2: A full renovation of all facilities back to peak performance configuration. 
  • Alternative 3: A new power generation facility higher up the canal at Luffman Spillway, with repairs and alterations to the canal further downstream to transition it to a stormwater conveyance facility. (This preserves EWEB water rights for power generation.) 
  • Alternative 4: A decommissioning of the canal, combining “stormwater conveyance” alterations to sections of the canal with the restoration of other parts of the Leaburg Project to pre-project conditions, including a new spillway at Johnson Creek and modification to the Luffman spillway.

Alternatives 1 and 2 are the most expensive due to extensive construction and repairs required throughout the entire project and facilities. They represent the two ends of the spectrum. Alternatives 3 and 4 are middle-ground options that balance costs with benefits. The four alternatives will be discussed in greater detail during the upriver Board of Commissioners meeting, which will be held on Tuesday, April 19 at 6 p.m. at the McKenzie Fire & Rescue Training Center (42870 McKenzie Highway).

“While EWEB and our consultants continue to study the alternatives, we will carry on with prioritizing reducing near-term risk because safety is EWEB’s first priority,” said EWEB Generation Manager Lisa Krentz. “Those measures will include reversible canal configuration changes, such as isolating portions of the canal from the high-flow creeks, and canal-wide efforts, such as proactive removal of unhealthy trees that could fall into the canal during a storm and obstruct water flow.”

On April 5, the Board of Commissioners approved the purchase of two properties along the canal that recently became available on the real estate market. Both properties are adjacent to the canal near to where EWEB expects to be constructing risk reduction improvements in the future. Purchasing these properties will ease construction access to work on the canal, whether that work involves canal restoration or decommissioning.