Related News
Related News
-
EWEB opens application for 2024 Electric Mobility Community Grants
Grant awards of up to $30,000 to cover costs associated with electric mobility projects.
Find Out More -
The Big Freeze 2024: After Action Report
Winter 2024 was one for the records books, and we'll look back on it for years to come and say, "That was a doozy!" The back-to-back January Ice Storms caused widespread damage to EWEB’s service territory, affecting approximately 38,000 customers. Preliminary repair costs were over $8 million, and additional repairs to transmission lines are still required.
Find Out More -
New tanks come online as EWEB modernizes water system
New drinking water storage tanks are one of several investments to ensure that EWEB can meet critical community needs in the event of an earthquake.
Find Out More -
Spring Cleaning? How about Spring Emergency Preparedness!
Spring is officially here and that means the plants are blooming, the sun is (sometimes) shining, and the grass is green! We've had our fair share of severe weather already, but spring weather is notoriously unpredictable. While you're in the midst of spring cleaning and garden care, consider completing these emergency preparedness tasks.
Find Out More -
EWEB General Manager Delivers 2024 State of the Utility
General Manager Frank Lawson delivered his address at the March 5 public Board of Commissioners meeting
Find Out More -
State of the McKenzie Watershed
EWEB’s Drinking Water Source Protection (DWSP) team says the McKenzie River continues to be an excellent source for drinking water.
Find Out More -
Nine days without power: My ice storm story as an EWEB customer and employee
While beautiful and peaceful, buying a home on the edge of the forest and surrounded by trees has its tradeoffs. Moving “upriver,” I knew there would be more threats to prepare for, including Mother Nature’s seasonal surprises.
Find Out More -
Preparation and Resilience: How EWEB Maintained Water Service During Recent Ice Storm
Learn about the projects and people that helped EWEB keep water flowing throughout the extreme weather event.
Find Out More -
EWEB achieves power restoration milestone over the weekend
Crews have so far restored power for 92% of customers who originally lost power at the height of the ice storm.
Find Out More -
Reenergized McKenzie River Valley transmission lines allow EWEB crews to restore power upriver
On Friday, a majority of EWEB crews tackled power restoration efforts upriver, after federally managed transmission lines were reenergized Thursday.
Find Out More -
EWEB estimates one week to complete power system restoration
On Wednesday, EWEB crews restored power for about 10,000 customers by repairing large equipment first.
Find Out More -
Second round of ice and ensuing thaw prompt mass power outages
On Wednesday, all EWEB crews, who have been working nonstop since Saturday, traversed EWEB’s service territory assessing the damage and restoring transmission lines and main power feeders.
Find Out More -
Power restored at EWEB’s water treatment plant
Crews restored electric power at EWEB's Hayden Bridge Water Filtration Plant Monday evening, allowing operators to switch off the generators and rely again on the grid. Meanwhile, EWEB crews brace for additional outages amidst second round of ice and during the coming thaw.
Find Out More -
EWEB crews making downed lines safe and restoring power across Eugene and the foothills
As EWEB works to restore electric service to customers affected by the ice storm, the customer-owned utility is following established policies and its “hierarchy of repair” to prioritize repairs that restore electric service to the greatest number of customers.
Find Out More -
Leaburg Decommissioning Action Plan
Plan details next steps through regulatory processes to begin dismantling Leaburg Dam by 2032.
Find Out More - Show More
Fixing the Unseen: Water Pipeline Replacement in Unincorporated Eugene
April 09, 2024 • Claire Wray, EWEB Communications
A new portion of pipeline is put into place by EWEB's water construction team.
--
How do you maintain 800 miles of something you can’t see? Sounds like a riddle, but this is everyday life for Chris Irvin, Water Engineer, and overseer of EWEB’s network of water distribution pipelines.
Water pipelines are buried underground, crisscrossing Eugene and delivering water to 63,000 homes and businesses. Many of the pipelines were installed from the 1950s to the 1970s and are inching closer and closer to the end of their useful lives. When charted out, replacement needs look like a bell curve, said Irvin.
“We're coming into the steep part of the curve,” he said. “A lot of our system is aging into the realm of replacement.”
To parse out what pipes need to be replaced first, Irvin relies on an internal model that uses data – like material, age, and history of breakage – to pinpoint pipelines that are most likely to fail. At the top of that list last year was a water pipeline on Azalea Drive in northwest Eugene. The pipeline had leaked and been repaired eight times since it was constructed in 1950.
EWEB's water distribution model.
Working with Independent Water Districts
The discovery presented a new riddle. How do you fix something that belongs to others?
The Azalea pipeline is in an unincorporated area of Eugene’s Santa Clara neighborhood. The pipes and fire hydrants are owned by an independent entity called the Santa Clara Water District. The SCWD buys wholesale water from EWEB and delivers it to customers through their self-owned pipeline network.
SCWD is governed by a volunteer board and doesn’t have any full-time employees. EWEB has a long-standing relationship with SCWD and provides planning, engineering, and construction services to help them maintain their water assets. SCWD pays EWEB for the services rendered, rather than going to an outside consultant for pipeline work.
“The district gets good bang for their buck in terms of how much pipe they get in the ground,” said Irvin, “because EWEB is adept at pipeline design and construction, and it alleviates the burden on the district to manage consultants and contractors.”
EWEB also benefits because it can ensure the quality of new pipe being added to the system. Although they have separate ownership, EWEB pipes and SCWD pipes are intertwined hydraulically, so consistency in design is important.
A Productive Partnership
The Azalea line that is being replaced was originally 6” in diameter that tapered down to 2” in some places. Construction is now underway to upsize the pipe to 8” and install new hydrants to improve water flow for firefighters. New standards for earthquake resiliency, like reinforced joints, are also being implemented. The project is estimated to cost a little under $300k, which will be paid by SCWD’s ~4,000 customers over time.
EWEB water construction workers fill a portion of the water pipeline trench on Azalea Drive.
Although it is a unique arrangement, Irvin said the partnership with SCWD is working well.
“They have the same bell curve problem as us,” said Irvin, “with all their pipes getting older and trying to spend money wisely. We've done a great job of replacing some pretty problematic pipes together over the last few years.”
EWEB has a similar partnership with the River Road Water District which serves unincorporated areas of Eugene’s River Road neighborhood.
For more information on how EWEB is working to safeguard your water, visit https://www.eweb.org/waterreliability.