Skip to Content

Related News

  • Related News

  • Upgrades to Eugene's downtown electric network continue

    You may have noticed construction this week on the corner of 7th and Pearl Street. That’s because crews replaced a corroded, aging vault with an innovative, new Voltek vault. The Voltek design allows for the new infrastructure to be built inside of the existing aging vault. We’re able to install the new vault while the cables are still energized, minimizing disruption to customers and traffic while cutting construction time in half.

    Find Out More
  • The Big Freeze 2024: After Action Report

    Winter 2024 was one for the records books, and we'll look back on it for years to come and say, "That was a doozy!"  The back-to-back January Ice Storms caused widespread damage to EWEB’s service territory, affecting approximately 38,000 customers. Preliminary repair costs were over $8 million, and additional repairs to transmission lines are still required. 

    Find Out More
  • New tanks come online as EWEB modernizes water system

    New drinking water storage tanks are one of several investments to ensure that EWEB can meet critical community needs in the event of an earthquake.

    Find Out More
  • Spring Cleaning? How about Spring Emergency Preparedness!

    Spring is officially here and that means the plants are blooming, the sun is (sometimes) shining, and the grass is green! We've had our fair share of severe weather already, but spring weather is notoriously unpredictable. While you're in the midst of spring cleaning and garden care, consider completing these emergency preparedness tasks.

    Find Out More
  • EWEB General Manager Delivers 2024 State of the Utility

    General Manager Frank Lawson delivered his address at the March 5 public Board of Commissioners meeting

    Find Out More
  • Show More
Commissioners Approve Resolution to Decommission Leaburg Hydroelectric Project

January 04, 2023 Adam Spencer, EWEB Communications

Leaburg Dam

EWEB Commissioners voted to decommission the Leaburg Hydroelectric Project at their first meeting of the year on January 3.

All five Commissioners voted to approve Resolution 2302, which directs the General Manager to develop a Leaburg Hydroelectric Project Decommissioning Action Plan (LDAP). The LDAP will guide staff in creating milestones for reporting progress to the Board and to determine a framework for how the Board can continue to provide oversight on the decommissioning process.

Commissioners also unanimously approved a Record of Decision in support of the “Management Recommendation: Future Disposition of the Leaburg Hydroelectric Project.”

The Recommendation advocates:

  1. permanently discontinuing electricity generation at the Leaburg Hydroelectric Project,
  2. removing Leaburg Dam and restoring the McKenzie to a free-flowing river in the project area,
  3. developing access to Leaburg Dam Road on the southern side of the river, preferably through Leashore Drive and the Goodpasture Bridge, if possible,
  4. repairing the Leaburg Canal for stream and stormwater conveyance (SWC), while preserving the future option to completely restore the site to pre-project conditions,
  5. working with water rights holders to mitigate the effects of dewatering the Leaburg Canal, particularly the Leaburg and McKenzie fish hatcheries,
  6. conducting a similar assessment of the Walterville Hydroelectric Project by the early 2030’s, and
  7. identifying opportunities and requirements for Board review, guidance, and direction moving forward.

Later in the meeting, Commissioners voted to approve the development of the LDAP as an organizational goal for 2023. Staff will provide quarterly updates on the Plan’s development.

General Manager Frank Lawson emphasized that decommissioning the project is a regulatory-driven process requiring several years of studies and negotiations with settlement parties before decommissioning construction activities will begin. Generation Manager Lisa Krentz added that the proposed timeline of beginning construction by 2033 is hopeful and that, to her knowledge, decommissioning projects routinely take longer than anticipated.

Leaburg Decommissioning Project Implementation Road Map

Meanwhile, staff will continue working on near-term risk-reduction measures on the Leaburg Canal.

Commissioners requested continued public outreach on the decommissioning process.

“As much information as we can get to the public – when we know or have a better idea – is important to me as a Commissioner,” said EWEB Board Vice President John Barofsky.

Throughout the year, EWEB staff will continue to provide updates through the Leaburg Canal Updates Newsletter, as well as scheduling meetings with interested groups to explain the implications of decommissioning on electricity rates, recreation, water rights, fisheries, and other considerations, as discovered. Staff will also advise interested parties how to participate in the negotiations between EWEB and various interest groups to develop a settlement agreement.

Once a settlement agreement is reached, EWEB will petition the Federal Energy Regulatory Commission (FERC) for approval and begin designing and permitting to begin decommissioning the project.

Watch the presentation and discussion, starting at 36:40: