EWEB is in the process of constructing two new water storage tanks and associated piping improvements near an existing water storage tank on North Shasta Loop. The project will enhance the reliability and seismic resiliency of drinking water service and is part of a multi-year plan to upgrade aging infrastructure.

About the Project

The area around Spring Blvd. is currently served from an existing 1.75-million-gallon steel tank built in the 1960s and a pump station, constructed in 2016, that runs 24 hours a day to provide water for fire suppression and domestic uses at the highest elevations. The current tank is 97 feet in diameter and 39 feet tall. 

The two new bolted glass-fused-to-steel storage tanks will each be 60 feet in diameter and 40 feet tall and have a combined capacity of 1-million-gallons. The tanks will be located at ground level. The site will be restored to meet the City of Eugene’s landscaping and screening standards.

Learn More: Project Timeline | Construction Update - Expect to See Drainage on Road | Email Updates | Frequently Asked Questions
About EWEB's Upper Level Reservoirs | Drinking Water Reliability


Project Timeline

aNorth Shasta Loop Upgrade Project Timeline

Trucking route for the North Shasta Loop Water Storage upgrade project.

Neighbor Impacts During Project

Construction activity will create noise, vibration, and dust near the construction site. Work will typically begin at 7:00 a.m. and conclude by 7:00 p.m., Monday through Friday, in accordance with the City of Eugene noise ordinance. Water service interruptions are not expected during this process.

Traffic Impacts

Construction trucks will travel from East 30th Avenue to the site entrance on North Shasta Loop. Please watch for trucks on this route, especially entering and exiting the construction site.







More Information on Eugene's Water Storage Projects

Water Storage Improvement Projects
Learn more

Learn more

The three primary tanks that store drinking water for all of Eugene are nearing the end of their useful lives and do not meet modern seismic standards. Learn how we are upgrading and diversifying water storage.

College Hill
Learn more

Learn more

EWEB is replacing the leaky and antiquated reservoir with new, modern drinking water storage tanks built to withstand major earthquakes. 

Water Reliablity Projects
Find out more

Find out more

We're making investments to prepare, replace and maintain our community's water system.