1. Electric Capital Improvement Project Update (2010-2014) – Dean Ahlsten, Manager Systems Engineering & Substation Reliability |
5:30 |
20 min. |
2. Water Capital Improvement Project Update (2010-2014) – Mel Damewood, Manager Water Engineering |
5:50 |
20 min. |
| 3. BPA Post-2011 Contract Amendments & Tier 2 Election – Dick Helgeson, Director Power Resources, and Eric Hiaasen, Mid Term Trader | 6:10 |
30 min. |
REGULAR BOARD MEETING |
||
|
||
| Start time | Length | |
| 1. Agenda Check (President Farmer) | 6:45 | 5 min. |
| 2. Public Input | 6:50 | 5 min. |
| 3. Approval of Consent Calendar (Items will be approved by one motion and without discussion. If discussion is required, specific items will be removed from the Consent Calendar and considered separately.) | 6:55 | 5 min. |
| 4. Items removed from Consent Calendar | 7:00 | 5 min. |
| 5. Items from Board Members | 7:05 | 10 min. |
| 6. Correspondence | 7:15 | 5 min. |
| 7. Board Agendas | 7:20 | 5 min. |
| 8. Electric Capital Improvement Plan (2010-2014) – Dean Ahlsten, Manager Systems Engineering & Substation Reliability | 7:25 | 10 min. |
| 9. Water Capital Improvement Plan (2010-2014) – Mel Damewood, Manager Water Engineering | 7:35 | 10 min. |
| 10. Citizens Advisory Team Preliminary Concept Presentation – Jeannine Parisi, Community and Local Outreach Coordinator | 7:45 | 45 min. |
| 11. Adjourn | 8:30 | |
Consent Calendar |
||
MINUTES 1. None to approve |
||
CONTRACTS 2. Motorola, Inc. – Spectrum Fingerprinting Services (to determine sources of radio interference) – Electric Division – $33,600. Contact person is Michael McElroy, 685-7344. 3. Stephen L. West, LLC – Consulting Services for Water Division Policy Updates – Water Division - $30,000. Contact person is Todd Simmons, 685-7373. 4. TekSystems – Temporary Staffing Services for Computer Operator Support – Corporate Services Division - $16,000. Contact person is Kim Spear, 685-7710.
|
||
REALLOCATION OF FUNDS 5. Community Care Funds – Reallocation of 2009 Funds (Approved in Budget Amendment #2 4-21-09), Outlined in Attached Memo – Debra Smith, Director Employee, Customer & Community Services, and Mark Freeman, Manager Customer Service.
|
||
CORRESPONDENCE 6a. Goodpasture Bridge Lighting Project |
||