Post 2006 BPA Resources -
Jim Wiley, Electric Division
Director, and Libby Henry, Legislative Representative
(Presentation - 30 min./Discussion - 30
min./Information)
Water Source Protection Update - Laurie Power,
Environmental Manager and Karl Morgenstern, Drinking Water Source
Protection Coordinator (Presentation
- 30 min./Discussion - 30 min./Information)
REGULAR BOARD MEETING
7:30 P.M.
Agenda check
(President
Anderson)
Approval of Consent Calendar
(Items will be
approved by one motion and without discussion. If discussion is
required, specific items will be removed from the Consent Calendar
and considered separately.)
Items from Board Members
(5 min.)
Correspondence
(5 min.)
Public input
Groundwater Bond Authorization -
Dick Varner
(Presentation - 10 min./Presentation -
10 min./Information)
Items removed from Consent
Calendar
Consent Calendar
February 5, 2002
Minutes of the November 20, 2001
Work Session, the December 4, 2001 Work Session and Regular Board
Meeting
Sybase Database
Management System - Information Services - Corporate
Services. Annual
renewal of Sybase maintenance agreement for adapting server
Enterprise data base software. Cost of the contract is
$25,321.50.Contact person is Greg Armstead, 484-2411,
ext. 3761.
The Ulum Group - Energy
Conservation Advertising - Public Affairs - Corporate
Services. Amendment
is needed to cover 2001 expenses for energy conservation
advertising production, Energy Share media buy, and Metro Net
marketing planning with The Ulum Group. All charges have been
previously budgeted, and will be coded to the 2001 budget.
However, we have exceeded the original amount of the contract with
The Ulum Group, which has precipitated this contract amendment.
The amount of the invoice for December, 2001 from The Ulum Group
is $133,177.22. We still have $19,119.10 remaining from the
original contract amount of $250,000 that we initiated in 2000.
The difference is $114,067.12, which is what we're
requesting in this consent calendar item for work done to
date. Amount spent to date is $364,068. Contact person is Marty
Douglass, 484-2411, ext. 3303.
OBEC Consulting
Engineers, Inc. - Engineering and construction inspection services
for City View 800 Reservoir No. 2 - Water Division.
Several additions to
the original scope of services for this project had had the
cumulative effect of increasing the contract to 127.6% of the
original fee estimate. The additional services included: expanding
the storage requirements study to encompass the entire 800'
service level; the design, bid documents and construction
management for the addition of retrofitting the existing City View
800 No. 1 Reservoir to have improved mixing and matched
hydraulics to the new reservoir, expanded participation in public
meetings; value engineering after the bid award to obtain cost
savings.
The original
contract amount was for $127,466. Subsequent amendments have
increased the contract to $152,266. The requested increase
is for an additional $10,440 for a total of $162,706 and
will complete the project. The contract increase was anticipated
in the 2002 budget for the project, therefore, no adjustments to
the budget are necessary. Contact person is Jay Bozievich,
484-2411, ext. 3237.
Delta - T, Inc. - HVAC
Maintenance Program - Energy Management Services - Customer
Service.Request for short-term contract extension with Delta T,
Inc. beyond the February 14, 2002 contract term, and to authorize
additional funds for the contract extension. Under the subject
agreement, Delta T provides duct diagnostic and sealing
services as a part of the HVAC Maintenance Program. The current
contract is scheduled to be re-bid this year. This contract
extension is necessary so that we can continue to provide
customers with duct sealing services while the bidding process on
the next contract is completed. Contract amount requested
is $20,000. Contact person is Bob Lorenzen, 484-2411,
3052..
Proctor Engineering Group
- HVAC Maintenance Program - Energy Management Services - Customer
Service. Request
is for approval to renew the business services agreement, and
increase the authorized funds with Proctor Engineering Group (PEG)
to provide engineering support for the CheckMe! Heat pump service
program. Under this contract PEG trains and licenses contractors
in the CheckMe! service protocol, and provides dial up diagnostic
assistance to licensed contractors at the time the technician is
conducting heat pump service. EWEB will pay for the cost of the
CheckMe! license and training for contractors. EWEB will also pay
PEG for the dial up assistance on a per call basis. This activity
is eligible for the Conservation & Renewable Discount credit
under our Power Sales Contract with Bonneville. Amount
requested is for $40,000. Contact person is Bob Lorenzen,
484-2411, ext. 3052.
The Energy Outlet -
Energy Management Services - Customer Service.
This
request is for approval of EWEB's 2002 contribution to the Energy
Outlet. Through a MOU (Memorandum of Understanding), EWEB, Emerald
PUD and Blachly-Lane Co-Op jointly provide funding assistance for
the Energy Outlet to support customer information and retailer
training activities. EWEB's contribution to the Energy Outlet is
fully eligible for the Conservation & Renewable Discount
credit under our Power Sales Contract with Bonneville.
Amount requested is $90,000. Contact person is
Bob Lorenzen, 484-2411, ext. 3052.
ECOS Consulting - ENERGY
STAR Lighting Program - Energy Management Services - Customer
Services. This
is a budgetary amendment to the business service agreement with
ECOS Consulting for administration of the ENERGY STAR Lighting
Coupon Campaign. This amendment authorizes funding of the Campaign
for the duration of the contract which continues through April 30,
20003. The services provided by ECOS under this agreement include
printing of coupons, and payment of retailers for redeemed
coupons. EWEB reimburses ECOS for redeemed coupons on a per coupon
basis that includes the face value of the coupon and a processing
fee. This activity is eligible for the conservation &
Renewable Discount credit under our Power Sales Contract with
Bonneville. Amount of contract is $600,000.
Contact person is Bob Lorenzen, 484-2411, ext.
3052.
Cascade Pacific Resource
Conservation and Development - McKenzie Watershed Protection
Program - Environmental Management - Corporate Services.
These are
funds from EWEB to continue support for the ongoing operations of
the McKenzie Watershed Council in 2002. The McKenzie Watershed
Council, co-founded by EWEB in 1991, is a voluntary organization
that serves to protect the multiple natural resources of the
McKenzie River. Cascade Pacific Resource Conservation and
Development provides fiscal management for the McKenzie Watershed
Council. The COG contracts directly with Jim Thrailkill to provide
staff services to the Council and with Kate Fershweiler to provide
watershed education services through December 31, 2001. The work
program for Jim and Kate is approved and overseen by the McKenzie
Watershed Council's Executive Committee of which EWEB is a
member.
Contributions to the
Council are also made by the Cities of Eugene and Springfield,
U.S. Forest Service, and Bureau of Land Management. The
council is also supported by a major grant from the Bonneville
Power Administration. EWEB has provided financial support to the
McKenzie Watershed Council since 1997. Amount of contract
is $24,000. Contact person is Laurie Power, 484-2411,
ext. 3313.
Dominion Power Services,
Inc. - Maintenance Services Contract Renewal - Smith Falls
Hydroelectric Project - Electric
Division.
This request is for approval to renew and award a five-year
contract. The existing contractor, DPSI, was a partner in the
Smith Falls Hydro company, which built the project in 1989. DPSI
has on-site employees who have operated and maintained the project
since construction. These employees helped build the project, are
intimately familiar with the operation and maintenance of the
project, and have had an excellent performance record as the
operators of the project. In addition, the contractor is aware of,
and complies with all Federal and Idaho laws and regulations, and
in particular, the project FERC
license.
Given that
the existing contractor is intimately familiar with the project,
the remoteness of the site, and the non-availability of qualified
contractors in the area, it is in EWEB's interest to retain DPSI
as the contractor for the operations and maintenance of the Smith
Falls project. In addition, the contract cost is competitive.
Approval of a new five-year contract is recommended. Cost
is $1,822,810 for the five years. Contact Jay L'Estrange
at 434-5751.
Heritage Research
Associates, Inc. - Leaburg-Walterville Relicensing - Electric
Division.The new Leaburg-Walterville license requires the
development of a Cultural Resources Management Plan (CRMP) and
Historic Structures Report for the Leaburg facility. The CRMP is
intended to provide a plan for EWEB to follow should the crews
find any culturally significant items as we conduct earth moving
activities in the future. In the report prepared for relicensing,
the Leaburg facility was identified as having historical
significance. The structures report will capture the history of
the facilities through preservation of drawings, photos, etc.
These are tasks that must be completed as a part of our federal
license and Heritage Research can complete these tasks more
efficiently and less costly than any other company or EWEB.
The work to be completed is on a very tight schedule and needs to
proceed as soon as possible. Despite the schedule, I would still
request the services of Heritage Research, since they
subcontracted to EA Engineering (the environmental consultants
that did all of our environmental studies required for
relicensing) for the cultural and historical evaluation. Heritage
Research is a local company that has extensive knowledge of the
area, McKenzie River, and EWEB's Leaburg-Walterville hydroelectric
project. Amount of contract is $27,860. Contact