AGENDA
EUGENE WATER & ELECTRIC BOARD
SPECIAL BOARD MEETING
(WORK SESSION)
EWEB BOARD ROOM
OCTOBER 5, 1999
5:30 P.M.
- 2000 Budget and Work Plan - Dick Varner, Fiscal Services
Supervisor, Mel Damewood, Water Engineering Manager, and Gale
Banry, Energy Resource Projects Manager
REGULAR BOARD MEETING
7:30 P.M.
- Agenda check (President Smith)
- Approval of Consent Calender (Items will be approved by
one motion and without discussion. If discussion is required,
specific items will be removed from the Consent Calendar and
considered separately.)
- Items from Board Members (5 min.)
- Correspondence (5 min.)
- Public Input
- Water Systems Development Charge proposal - John Yanov, Senior
Rate/Financial Analyst (Presentation - 15 min./Discussion - 10
min./Information)
- First Public Hearing on Water Systems Development Charge
proposal (15 min.)
- Black & Veatch's five-year utility report on properties
and operations - Bob Brady, EWEB's Independent Engineer and
representative of Black & Veatch (Presentation -
10 min./Discussion - 10 min./Information)
- Wind power rate for industrial and large commercial customers
- Mat Northway, Energy Management Services Manager (Presentation -
5 min./Discussion - 5 min.)
- Public Hearing on industrial and large customer wind rates (5
min.)
- Wind power rate for industrial and large commercial customers
- Mat Northway (Action)
- Major Customer Meeting - Mike Logan, Section Manager of
Commercial/Industrial Programs, Energy Management Services
(Presentation - 5 min./Discussion - 5 min./Information)
- Items removed from Consent Calendar
Consent Calendar
Items for Approval
October 5, 1999
MINUTES
- Minutes of the September 7, 1999 Work Session and Regular
Board Meeting
PERSONAL SERVICE CONTRACTS
- Black & Veatch, Phase I Telecommunications -
Electric Division. This is for engineering and business
related support and guidance in the development and design work
associated with the Telecommunications Project Phase I and
provided between February 1998 and November 1999. Work includes
support and analysis for development of business strategies and
business plan, electric utility telecommunication applications,
Phase I design; special assistance in structural analysis of
certain steel transmission towers and foundations; and completion
of independent assessment of Phase design and final cost estimate.
The major portion of this work has been completed. (Contact person
is Ken Beeson, 341-3772)
- Applies to
- 1999 Budget
- Budgeted amount (Job No. 17738) $9,364,263
- Amount of this contract $ 120,000
- Estimated Year-End expenditures (Job No. 17738)
$6,900,000
CONTRACT AWARD
- EA Engineering, Science and Technology, Inc. -
Electric Division. EWEB has been designated by FERC as
its non-federal representative for Endangered Species Act (ESA)
Section 7 consultation with the federal fisheries agencies
regarding EWEB's hydroelectric projects on the McKenzie River.
EWEB is responsible for developing a Biological Assessment (BA)
document that addresses project affects on ESA listed fish
species, bull trout and spring chinook salmon. The EA team will
prepare the BA ad assist EWEB with associated agency negotiations.
The EA team was judged to be the most qualified by staff after a
competitive RFP process. They were also the lowest bid. Funding
will come from the Electric Division. Contract work will extend
into FY 2000 and is being budgeted. Money for this contract will
be from capital work deferred this year. (Contact person is
Everett Jordan, 484-2411, 3205)
- Applies to
- 1999 Budget
- Budgeted Amount $ -0-
- Additional Funds needed for this Project $ 50,000
- % of Project Complete 0%
- Items is not budgeted under Job No. 20180
- Arbor Tree Surgery - Tree trimming in EWEB
service area - Electric Operations. A three year contract with the
option to extend the contract to five years. (Contact person is
Dave Koski, 484-2411, 3731)
- Applies to
- 2000 Budget
- Contract Amount $898,000
- Item budgeted under Job No. 759
-
CONTRACT AMENDMENT
- Weyerhaeuser No. 4 Turbine Maintenance - Electric
Division. The budget is $284,529 to fund a six-year
planned maintenance overhaul of Weyerhaeuser No. 4
Turbine/Generator. Under our existing contract with Weyerhaeuser,
all costs for the operation and maintenance of #4 turbine
generator is shared equally with Weyerhaeuser. As a result,
Weyerhaeuser will pay for ½ of the costs for the overhaul,
including the overrun. The overhaul took place during July of this
year and all invoices have been received. The total costs of the
maintenance overhaul is $509,280, which is $224,751 over budget.
EWEB's practice has been to budget for the predictable maintenance
activities and deal with the extra work related to worn and
damaged components as they are discovered during the overhaul.
Staff is reviewing that practice for further maintenance cycles.
Weyerhaeuser will reimburse EWEB for half of the $224,751
($112,375) cost overrun. EWEB's portion will come from deferred
maintenance. (Contact person is Everett Jordan,
484-2411, 3205.)
- Applies to
- 1999 Budget
- Total Cost of Overhaul $509,280
- Budgeted Amount $284,529
- Cost Overrun $224,751 (only half is EWEB's)
- Additional EWEB funds needed $112,375
- Percent of Project Completed 100%
BUSINESS SERVICE AGREEMENT
- PricewaterhouseCoopers - Electric and Water Utility
and Trojan Project Annual Audits - Finance
Division. This is the end of a five year contract with
PricewaterhouseCoopers. We will be initiating a request for
proposal for the 2000 audits. Contact person is Cathy Bloom,
484-2411, ext. 3277)
- Applies to
- 1999 Budget
- Budgeted amount $66,800 (for E & W utilities)
- $ 6,240 (Trojan)
- Additional Funds Needed $ -0-
- Items are budgeted under Job Nos. 14931
- and 334 (Trojan)
- Bond Trust Accounts - Financia Division.
Agreement for the 1999/2000 Trustee fees of $30,000 for
Bond Trust accounts. Money is required to be held in trust in
accordance with the Bond Resolutions. (Contact person is Cathy
Bloom, 484-2411, 3277)
- Applies to
- 1999 Budget
- Budgeted amount $30,000
- Additional Funds Needed $ -0-
- Item is budgeted under Job No. 238