EWEB Home > What's New > Carmen-Smith Relicensing Project > Timetable
Relicensing timetable
The Federal Energy Regulatory Commission has established a three-stage Traditional Licensing Process to ensure that all appropriate entities and the public are consulted prior to issuing a new license.
However, in order to meet its objectives for sharing information and involving stakeholders in the process, EWEB is taking additional steps beyond what is required in the Traditional Licensing Process.
For more information about when various components of the relicensing process are scheduled to start and finish, a Relicensing Timeline is available in pdf format.
Below are the key steps and decision points in the relicensing process:
| Key EWEB activity |
Timetable |
| Notice of intent filed with FERC |
July 21, 2003 |
| Development of the Public Library |
June 1, 2003 to July 21, 2003 |
| Agency and public consultation |
October 2003 to November 2006 |
| Scoping of studies to conduct |
October 2003 to early 2004 |
| Conduct necessary studies |
Early 2004 to early 2006 |
| Submit water quality permit application |
Nov. 29, 2006 |
| Submit Draft License Application |
May 11, 2006 |
| Develop Final License Application |
Nov. 30, 2006 |
| |
|
| Key FERC activity |
Timetable |
| Environmental review notice |
Mid-2007 |
| Scoping of Environmental Assessment or Environmental Impact Statement |
Mid-2007 to mid-2008 |
| Completion of NEPA document |
Mid-2008 |
| Endangered Species Act consultation |
Early 2007 to mid-2008 |
| Issuance of new license (or denial) |
Nov. 30, 2008 |
|