AGENDA
EUGENE WATER & ELECTRIC BOARD
SPECIAL BOARD MEETING
(WORK SESSION)
EWEB BOARD ROOM
MARCH 20, 2001
5:30 P.M.
- Update on EWEB Headquarters Site Master Plan: Review Site
Options and Discuss Public Involvement Process, Deborrah Brewer,
Project Manager and Susan Goltsman, MIG Inc.
SPECIAL BOARD MEETING
7:30 P.M.
- Agenda Check (President Anderson)
- Approval of Consent Calendar (Items will be
approved by one motion and without discussion. If discussion is
required, specific items will be removed from the consent Calendar
and considered separately.)
- Items from Board Members (5 min.)
- Correspondence (5 min.)
- Public Input
- Large Customer Curtailment/Generation - Dick
Varner, Fiscal Services Supervisor, and Jim Bemis and Steve Hill,
Key Account Managers (Presentation - 5 min./Discussion -
5 min./Action)
- Discussion on BPA Subscription Alternatives -
Scott Spettel, Power Management and Planning
Manager and Eric Hiaasen, Power Marketing Analyst (Presentation -
10 min./Discussion - 10 min./Information)
- Electric Supply Issues (Tieton, Stateline, and EWEB Steam
Plant) - Scott Spettel (Presentation -
30 min./Discussion - 30 min./Action)
- Public Bidding Exemption - Steam Plant Repowering Project -
Scott Spettel (Presentation - 5 min/Discussion - 5
min./Information)
- Bonneville Environmental Foundation - Green Credit Request -
Jim Maloney, Energy Resources Project Manager
(Presentation - 5 min./Discussion - 5 min./Action)
- Items removed from Consent Calendar
Consent Calendar
March 20, 2001
MINUTES
- Minutes of the February 9, 2001 Work Session
and the February 20, 2001 Work Session and Special Board
Meeting
BUSINESS SERVICES AGREEMENTS
- Qwest Joint Use Pole Annual Rental Fee - Facilities
Services. This is an annual fee paid to
Qwest for EWEB electric attachments to Qwest owned poles. Total
cost for the contract is $20,358.36. Amount requested is $348.36.
Contact Mark Oberle, 484-2411, ext. 3230.
- Capital Advisors, LLC - Financial Advisory Services -
Financial Services. Seagraves & Hein
Capital Advisors, LLC, the company originally awarded the contract
for Financial Advisory Services has no split with Christine Hein
Pihl, a partner and our principal contact in Seagraves & Hein.
She is now the principle in Capital Advisors, LLC. Christine is
familiar with all of the projects and with EWEB concerns.
Seagraves & Hein's performance was reviewed as part of the
annual Board appointment process for 2001, and was found to be
excellent. It is in EWEB's best interest to continue working with
Christine. The estimated cost of this contract for 2001 is
$80,000. Contact is Jim Origliosso, 484-3753.
- Lane County Waste Department Dump Sites - Maintenance
- Facilities Services. This contract is
for the annual fees for $36,000 per year for five years for use of
the Lane County Waste Department Dump sites. Contact person is
Charlie Morris, 484-2411, ext. 3223.
- EOS Consulting - Energy Star Lighting coupon Champaign
- Energy Management Services - Customer Services
Division. This request is for approval to
enter into a BSA with ECOS to administer a compact flourescent
lighting (CFL) program that offers customers a $6 coupon for the
purchase of an Energy Start Compliant CFL;s, This is a new
regional program that has been developed in the last several
months by Bonneville in response to regional energy crisis. ECOS
Consulting, which has been a contractor to the Northwest Energy
Efficiency Alliance (NEEA) for NEEA's Energy Star Lighting
Program, was chosen by Boinneville to be the regional
administrator of the Lighting Coupon Campaign. This budget
estimates over 42,000 coupons will be redeemed by EWEB customers
this year. This program was not planned in the 2001 budget
process. This program represents an expenditure beyond the planned
2001 conservation investments. Contact person is Bob Lorenzen.
Cost of the Contract is $300,000.
BID AWARDING
- Cutler-Hammer Company - Network Protector Upgrading
Program - Eugene Library and TelecommLocate Project - Electric
Division. Competitive bids were
solicited for a multi-year downtown network program.
- A five-year network protector upgrade program
with a vendor to replace/rebuild EWEB's network protectors to
maintain the reliability of the downtown network system. EWEB
anticipates rebuilding/replacing all network protectors during the
next five years.
- The purchase of a total of five new network
protectors in 2001 to serve the new public library building and
TelecommLocate facility in downtown Eugene.
Electric Engineering recommends awarding this
contract to the low bidder, Cutler-Hammer Company.
The contract for upgrading network protectors
would be awarded for a five-year period. During this contract term,
the program would allow EWEB to refurbish the absolete network
protectors to ensure reliable operation for the next 30 years.
This is a requirements contract and purchases will
be made on an as needed basis. Unit pricing has been established for
all network protectors (both new and rebuilt). Number of units
pruchased may or may not exceed the estimates provided herein. (See
memo for breakdown) Cost of the contract is $238,000. Contact Dean
Ahlsten, 484-2411, ext. 3210.
CONTRACT EXTENSION
- Laurel Hill Center (SWEEP) Contracted Services,
Headquarters Site - Facilities
Services. This contract
is for an additional $36,000 to extend the existing contract with
Laurel Hill Center (SWEEP) for janitorial services for the
headquarters Site and Hayden Bridge Filtration Plant for April 1
through June 30. ( A request to extend the contract from January 1
through March 30, 2001 was granted January 16, 2001) A request for
proposal is currently out to potential QRF contractors with a
closing date of March 19. It is anticipated that the evaluation
process will take about two weeks. It is likely that a new
contractor will not be able to begin work by March 31. In
addition, if an equitable contract cannot be negotiated with any
of the responding QRF contractors the RFP will be reissued to
non-QRF contractors, which will extend the selection process
another four-to-six weeks. This contract extension allows service
to continue without interruption until a new contract is put in
place. Contact person is Charlie Morris, 484-2411, ext. 3223.